  S.N. Clients Project Scope of Works Approx. Value, US $ Period
72 Nepal Electricity Authority Chapali 132kV Substation Expansion Supply, Construction and Installation of 132/66kV Chapali Substation and associated works, ADB funded 8,100,000 Sept 2014- January 2017
71 Nepal Electricity Authority DCS, Butwal Regional Office Repairing of Distribution Transformers 60,000 Aug 2015-Jul 2016
70 Synergy Power Development Ltd. 9.6MW Siprin Khola Power Plant Mnaufacturing, Repairing and Installation of Hydro -mechanical components damaged by recent Quake 200,000 Jun-Aug 2015
69 Marusin Sitaka Corporation Rani Jamara Kuleria Manufacturing and Installation of Stoplogs 1,200,000 Nov 2012-Apr 2015
68 Nepal Electricity Authority Grid Operation Department Supply and installation of 16 MVA Transformer Bay at Chanauta Substation      270,000 Apr 2014 - Mar 2015
67 Butwal Power Company Ltd. Rangkhola Substation Supply and installation of 33 kV Rangkhola Interconnection Switching Station      155,000 Jul 2014-Feb 2015
66 Butwal Power Company Ltd. 9.4 MW Andhi Khola Project (Upgrading) Design, supply, manufacturing and installation of Penstock pipes and HM Works 1,160,000 Jan 2011 – Jan 2015
65 Nepal Electricity Authority Butwal – Kohalpur 132 kV Corridor Design, Supply, Construction, Installation and commissioning of 132 kV Substations, funded by ADB 6,200,000 Jan 2011 – Dec 2014
64 Nepal Electricity Authority Grid Operation Department Supply, Construction of 132/11 kV, 30MVA at Pokhara and 33/11kV, 16.6 MVA Transformers Bay  at Damauli Substations. 730,000 May 2013- April 2014
63 Nepal Electricity Authority Grid Operation Department Supply, Construction of 33/11kV, 16.6 MVA Transformers Bay at Dhalkebar Substation. 270,000 May 2013- April 2014
62 Nepal Electricity Authority Chandranigahpur Substation, Grid Operation Extension of  30 MVA, 132/33 kV Chandranigahpur Substation  500,000 Dec 2012 - Feb 2014
61 Nepal Electricity Authority 32 MW Kulekhani 2 Hydropower Plant Supply of 37.8 MVA, 6.6/132 kV Transformer 370,000 Apr - Dec 2013
60 DoLIDAR, Govt. of Nepal Shani–Bheri Motorable Steel Truss Bridge Fabrication and Erection of Shani – Bheri Motorable Steel Truss Bridge 230,000 Aug 2009 - Mar 2013
59 Synergy Power Deve. Pvt.  Ltd. 10 MW Siprin Khola Hydro-mechanical Equipment works 420,000 Jun 2009 – Nov 2012
58 Nyadi Group Pvt. Ltd. 5 MW Siuri Khola Hydro-mechanical Equipment works 600,000 Jun 2009 – Sept 2012
57 Nepal Electricity Authority Lamahi Substation Supply and Installation of 30 MVA, 132/33 KV  Power Transformer Bay      400,000 Jan  -  Oct 2012
56 Nepal Electricity Authority                 System Reinforcement, Power Development 33/11 kV Sub-stations under Contract No. ICB-DSR01/2008 - 2, Lot 1 (the World Bank funded) 1,900,000 Jan 2011 – Jun 2012
55 Grid Operation Dept., NEA Parwanipur Substation Supply, and Installation of 45MVA, 142/66 kV Transformer Bay  800,000 Jun 2010 – Aug 2011
54 Nepal Electricity Authority                 System Reinforcement, Power Development 33/11 kV Sub-stations under Contract No. ICB-DSR01/2008-2, Lot 2 (the World Bank funded) 2, 500,000 Apr 2010 – Oct 2011
53 Kathmandu University Turbine Test Lab Supplying, Installation and Commissioning of Hydro-mechanical equipment 390,000 Mar 2010 – Aug 2011
52 Himal Power Limited 60 MW Khmiti1 Power Station Reclamation of 3 nos. of 12 MW Pelton Runners 190,000 2009 - 2010
51 Nepal Electricity Authority 14 MW Modikhola  Hydropower Station Manufacturing and Supplying of Francis Guide Vanes and other Pats of Turbine 130,000 2010
50 Nepal Electricity Authority 70 MW Marsyangdi Hydropower Station Design, supply and installation of hydraulic gate parts 80,000 2010
49 Nepal Electricity Authority 10 MW Sunkoshi Hydropower Station 6.3 MVA, 6.6/72.6 kV Power Transformer 140,000 2010
48 Hwachon Plant Constn. Ltd., Korea 30 MW Chameliya Project Supply and Delivery of Earthing materials 78,000 2010
47 Nepal Electricity Authority 144 MW Kali Gandaki ‘A’ Hydropower  Station 5MVA, 132/11kV, Transformer 220,000 2009 – 2010
46 Nepal Electricity Authority Grid Operation Department 132/33 kV, 63 MVA Power Transformer at Butwal Substation 650,000 2009 – 2010
45 Himal Dolakha HP Co.  Pvt. Ltd. 4.5 MW Lower Mai Hydropower Project Penstock Pipes and HM equipment 610,000 2008 - 2010
44 Himal Power Ltd. 60 MW  Khmiti1 Power Station  Reclamation of 3 nos. of 12 MW Pelton Runners 165,000 2008 -  2009
43 Butwal Power Co.  Ltd. 3 MVA, 33/11 kV Mirdi   Substation   3 MVA, 33/11 kV Mirdi   Substation equipment 250,000 2008 - 2009
42 Nepal Electricity Authority Sindhu Dolakha D/Line Extension  Supplying of steel telescopic poles 180,000 2009
41 DDC, Dhading, GoN Timilsena Gaun-Dangal Danda Suspended Bridge  Design, Fabrication and delivery of Steel Parts 38,000 2009
40 Butwal Power  Co. Ltd. Jhimruk Hydropower Plant Supply and  installation of  6/8 MVA, 6.6/33 kV Transformer 167,000 2009
39 Druk Green Power Corporation Ltd, Bhutan Basochhu Power Station – Phase II  Repairing of broken bucket of 22 MW Pelton Runner 38,000 2009
38 KAAA, Pokhara Micro Hydropower 45 and 15 kW MH & EM equipment 80,000 2009
37 Nepal Electricity Authority Grid Operation Dept. 45 MVA, 132/66kV Transformer & Line Bay 1,500,000 2007 –  2009
36 33/11 kV, 16.6 MVA Transformer at Butwal Substation 570,000 2007 – 2009
35 132 kV Busbar Re -arrangement" under Contract No. GOD/2063/64-03. 460,000 2007 -  2009
34 ANK Construction / Dept of Road, GoN Rapti Bridge, Nepalgunj - Bhagauda Road Fabrication and erection of steel truss 6 x 50m  span bridges 170,000 2002 - 2009
33 Alstom Power, Germany 70 MW Middle Marsyangdi, Lot E Assembling of 2 x 36 MW Generators and erection of 12 kV generation  control & protection panels and  switchgear 660,000 2004 -  2008
32 Andritz Hydro GmbH, Austria 70 MW Middle Marsyangdi, Lot HSS Fabrication and erection of Penstock Pipes of 5.5m dia & 450m long, total 1,800 tons 680,000 2004 -  2008
31 MCE Industrietechnik  GmbH & Co, Austria Erection of Hydraulic gates, Trashracks, Stoplogs and structures – 1,800 tons 590,000 2004 - 2008
30 Andritz Hydro GmbH, Austria  Fabrication of Hydraulic gates, trashracks and structures, total 1,800 tons 680,000 2004 -  2007
29 Nepal Electricity Authority TL/Substation Constn. Department Design, Supply and Construction of 30 MVA, 132/33 kV Chandranigahpur Substation 2,500,000 2006 – 2 008
28 Druk Green Power Corpn. Ltd., Bhutan 336 MW Chhukha Hydro Power Station Reclamation of 3 nos. of 84 MW of Pelton Runner (3.6m dia & 16 tons) 275,000 2006 –  2008
27 Nepal Electricity Authority DCS, Dolakha Branch Design, construction, supply, installation and commissioning of 1.5 MVA, 33/11 kV Kirne Substation 315,000 2006 -   2007
26 Nepal Electricity Authority Community Rural Electrification Dept. Design, Supply and Construction of 11/0.4 kV Power Lines 750,000 2005 – 2007
25 Nepal Electricity Authority Grid Operation Dept. Construction of 132/33 kV Transformer Bay and Repair of 10 MVA Transformer at Damauli 195,000 2006 – 2007
24 Nepal Electricity Authority Grid Operation Dept. Repairing and Installation of 20MVA Transformer at Lahan 180,000 2006 – 2007
23 Nepal Electricity Authority Generation Operation & Maintenance Dept. 132/33 kV, 15 MVA Switchyard Expansion at Modi Hydro Power Station 610,000 2006 – 2007
22 Mitsui & Co. Ltd./ Toshiba Corporation, Japan 144 MW Kali Gandaki "A", NEA Reclamation of 2 Francis Runners (each  2.6m dia and 8 ton), 100 nos. of Wicket Gates, Upper/Lower Wearing Rings 253,000 2006
21 Khudi Hydropower Ltd. 4 MW Khudi Hydro- mechanical works and 2.5 km Penstock Pipes 970,000 2005 – 2006
20 Nepal Electricity Authority Grid Operation Dept. 15 MVA, 66/11 kV Transformer Bay at Birgunj substation 340,000 2005 – 2006
19 Nepal Electricity Authority Grid Operation Dept. 132 kV Kusaha Switching Station   147,000 2005 – 2006
18 Voith Siemens GmbH, Germany 70 MW Middle Marsyangdi, Lot M Fabrication of  Draft Tube Lners, Spiral Casings, Stay Rings and pit liners for 2 x 35 MW vertical Francis Turbines  200,000 2002 - 2005
17 Rairang Hydropower Dev. Co. Pvt. Ltd. 500 kW Rairang Fabrication, erection, testing and commissioning of Manifold, Penstock Pipes 114,000 2003 - 2004
16 Shakti Hardwares/ Dept of Road, GoN Rapti Bridge, Dang Fabrication and erection of steel truss 7 x 48m long bridges, total 7 x 120 tons 170,000 2001 - 2002
15 Nepal Electricity Authority Modi Khola Substation 5 MVA, 132/33 kV substation equipment 214,000 2002 - 2003
14 Nepal Electricity Authority Panchkhal Substation 5 MVA, 66/11 kV substation equipment 348,000 2002 - 2003
13 Himal Power Limited 60 MW Khimti 1 70 MVA, 11/132 kV Switchyard 875,000 1998 - 2000
12 VA TECH Hydro Ltd., India 20 MW Chilime, Lot  3 Erection of 2 x 10 MW EM equipment and 28 MVA, 11/66 kV Switchyard 110,000 2001 - 2003
11 Chilime Hydropower Co. Ltd. 20 MW Chilime, Lot HMW Design, manufacture and erection of gates, stoplogs and trashracks.   270,000 2000 - 2003
10 Larsen and Toubro Ltd., India 20 MW Chilime, Lot C Manifold, Y-type Bifurcation and penstock Pipes 1,000,000 2000 - 2003
9 Alstom Power, France Kali Gandaki "A" Lot 5 Erection of 3 x 56.5MVA and a 5MVA Power Transformers, 132 kV GIS and 12 kV Breakers. 125,000 2000 - 2001
8 Hyundai Engineering Co., Ltd., Korea 14 MW Modi HM and EM equipment including 18 MVA, 11/132 kV Switchyard at  Pokhara 140,000 1999 - 2000
7 Nepal Electricity Authority 6.2 MW Puwa Design, manufacturing and installation penstock pipe and HM Equipment 660,000 1997 - 2000
6 DSD Noell GmbH, Germany Kali Gandaki “A”, Lot 4 Fabrication of sluice way steel liners, Extension of Sluice way liners and bulkheads   1998 - 1999
5 Himal Hydro & General. Construction Ltd. Mankamana  Cable Car  Fabrication of 20 sets of steel towers (15 - 45 m high) for cable car system 160,000 1998
4 Butwal Power Company Ltd. 12 MW Jhimruk HM, EM  equipment and 15 and 3 MVA Transformers including 132 kV switchyard  1,330,000 1991 - 1994
3 Nepal Electricity Authority 250 kW Darchula 250 kW Francis turbine and complete Electro-mechanical Equipment 110,000 1992
2 Butwal Power Company Ltd. 5.1 MW Andhikhola Design and Manufacturing of Hydro-mechanical equipment 1,050,000 1987 - 1990
1 Installation and commissioning of HM and EM  equipment