A pioneer engineering company of Nepal

Chhukha Hydropower Runner, 336 MW

Name of Project                     

Chhuka Hydropower Plant, 4x84MW                                   

Project Location

Chhuka, Bhutan

Employer 

Druk Green Power Corporation Limited

Contract No. 

CHPCL/0&MW/06/2006

Period

2007-2008

Worn out runner Buckets before dispatch to Butwal Works
Grinding of Runner Bucket
Welding of Runner Bucket after Grinding
Maintaining the temperature during Runner Bucket Welding
Mr Wangdi inspecting Runner Profile
Runner being put in Heat Treatment Chamber
Reclaimed Runner ready for delivery
Packed Runner ready for Transportation to Chhuka, Bhutan
Technical Negotiation Meeting with Mr Lam Dorjee, Plant Manager
Commercial Negotiation Meeting with Dasho Yeshi Wangdi, MD
Contract signing and exchanging the Documents, Former Service Division Manager Mr Laxmsn Devekota and Mr K Namgay, Chhuka Plant Manager
Contract signing and exchanging the Documents, Former Service Division Manager Mr Laxmsn Devekota and Mr K Namgay, Chhuka Plant Manager