Chandranighapur Substations Reinforcement Project

Name of Project Chandranighapur Substations Reinforcement Project
Project Location Chandranighapur, Gaur and Haripur
Employer Nepal Electricity Authority, Transmission & Substation Construction Department
Contract No. ICB - CSR 2005/06 - 1 (IDA LOAN No.Cr.3766-NEP/Gr.H039-NEp)
Scope of Works Design, Supply, Construction, Testing and Commissioning of 30 MVA, 132/33/11KV Substation at Chandranighapur and 33 kV Bay Extension at Gaur and Haripur Substations, funded by the World Bank
Contract Value (Approx) USD 2,214,000 + NPR 71,000,000
Contract Period August 2006 – July 2008
Project Execution NHE in Joint Venture with CWE (China International Water & Electric Corporation), China
30 MVA, 132 kV Bay
132 kV Outgoing Transmission Line Tower
30 MVA, 132 kV Power Transformer
Control Building
6/8 MVA, 33 kV Bay
Battery Charging Units and 132 kV Control & Protection Panels
33 kV Vacuum Circuit Breakers for Outgoing Lines
ABB RTU and Siemens PLCC